Construction Progress

Drone video footage: Dated Nov 2019

Stages 1,2, 3,  4 and 5
Now All Registered for Title!

Construction works have all completed within Stage 5, and this stage has now titled.

Stages 6 – 9

Programming for works in stages 6 – 9 is now underway. We expect information regarding these stages to be available and communicated soon.

 

Stage 1

Construction Complete
100%
Forecast Completion: Stage Titled
* Titles are expected within 6 weeks of construction completion
Construction Phase Completed

Stage Planning and Permits

Council and Relevant Authority acceptance and approval of documentation, including engineering design to allow for Stage work to commence on site.
Complete

Bulk Earthwork

Earthworks for construction of the Stage.
This work includes removing topsoil and the cutting and filling of the land within the Stage to achieve suitable surface levels for roadways and each lot.
Complete

Drainage

The construction and installation of underground drainage services.
These services include the provision of drainage for roads, public areas and a drainage point for each lot within the Stage
Complete

Sewer

The construction and installation of underground sewer services.
Sewer works include the provision of trunk sewers and the reticulation of sewer pipelines. Sewer connection points are provided to each lot within the Stage.
Complete

Water and Gas Services

The installation of water and gas pipelines. Connection points are provided to each lot within the Stage.
Complete

Road Boxing, Kerb and Channel

Ground preparations. Construction of base and lower layers of roads. Build kerbs to border the roadways and channels for drainage of rainwater.
Complete

Electrical and NBN

The installation of electrical services and NBN (for high-speed internet) with connection points provided for lots within the Stage.
Complete

Footpaths and Asphalt

Preparation of ground surfaces for the installation of footpaths. Install footpaths and topsoil nature strips within the Stage. Construction of middle pavement layers and asphalt road surfaces.
Complete

Practical Completion

Stage Construction Works are Complete
Complete

Statement of Compliance

Council and Relevant Authorities complete audit and inspections. Roads and services are approved. Council provides Statement of Compliance confirming works are complete per the approved plans and to the satisfaction of all Relevant Authorities
Complete

Titles and Settlement

Registration of Titles for each lot by Land Titles Victoria as per the plan of subdivision and the surveyor's report. With the legal transfer of the lot to the developer to the purchaser on settlement
Titled
Disclaimer: Please note that all timeframes are estimated only, are reviewed constantly and are often subject to third party approvals and works occurring as scheduled, and do not take inclement weather into consideration.

Stage 2

Construction Complete
100%
Forecast Completion: Stage Titled
* Titles are expected within 6 weeks of construction completion
Construction Phase Completed

Stage Planning and Permits

Council and Relevant Authority acceptance and approval of documentation, including engineering design to allow for Stage work to commence on site.
Complete

Bulk Earthwork

Earthworks for construction of the Stage.
This work includes removing topsoil and the cutting and filling of the land within the Stage to achieve suitable surface levels for roadways and each lot.
Complete

Drainage

The construction and installation of underground drainage services.
These services include the provision of drainage for roads, public areas and a drainage point for each lot within the Stage.
Complete

Sewer

The construction and installation of underground sewer services.
Sewer works include the provision of trunk sewers and the reticulation of sewer pipelines. Sewer connection points are provided to each lot within the Stage.
Complete

Water and Gas

The installation of water and gas pipelines. Connection points are provided to each lot within the Stage.
Complete

Road Boxing, Kerb and Channel

Ground preparations. Construction of base and lower layers of roads. Build kerbs to border the roadways and channels for drainage of rainwater.
Complete

Electrical and NBN

The installation of electrical services and NBN (for high-speed internet) with connection points provided for lots within the Stage.
Complete

Footpaths and Asphalt

Preparation of ground surfaces for the installation of footpaths. Install footpaths and topsoil nature strips within the Stage. Construction of middle pavement layers and asphalt road surfaces.
Complete

Practical Completion

Stage construction works are complete.
Complete

Statement of Compliance

Council and Relevant Authorities complete audit and inspections. Roads and services are approved. Council provides Statement of Compliance confirming works are complete per the approved plans and to the satisfaction of all Relevant Authorities
Complete

Titles and Settlement

Registration of Titles for each lot by Land Titles Victoria as per the plan of subdivision and the surveyor's report. With the legal transfer of the lot to the developer to the purchaser on settlement.
Stage Titled
Disclaimer: Please note that all timeframes are estimated only, are reviewed constantly and are often subject to third party approvals and works occurring as scheduled, and do not take inclement weather into consideration.

Stage 3

Construction Complete
100%%
Forecast Completion: Titled
* Titles are expected within 6 weeks of construction completion
Construction Phase Completed

Stage Planning and Permits

Council and Relevant Authority acceptance and approval of documentation, including engineering design to allow for Stage work to commence on site.
Complete

Bulk Earthwork

Bulk Earthwork
Earthworks for construction of the Stage.
This work includes removing topsoil and the cutting and filling of the land within the Stage to achieve suitable surface levels for roadways and each lot.
Complete

Drainage

The construction and installation of underground drainage services.
These services include the provision of drainage for roads, public areas and a drainage point for each lot within the Stage.
Complete

Sewer

The construction and installation of underground sewer services.
Sewer works include the provision of trunk sewers and the reticulation of sewer pipelines. Sewer connection points are provided to each lot within the Stage
Complete

Water and Gas

The installation of water and gas pipelines. Connection points are provided to each lot within the Stage.
Complete

Road Boxing, Kerb and Channel

Ground preparations. Construction of base and lower layers of roads. Build kerbs to border the roadways and channels for drainage of rainwater
Complete

Electrical and NBN

The installation of electrical services and NBN (for high-speed internet) with connection points provided for lots within the Stage.
Complete

Footpaths and Asphalt

Preparation of ground surfaces for the installation of footpaths. Install footpaths and topsoil nature strips within the Stage. Construction of middle pavement layers and asphalt road surfaces.
Complete

Practical Completion

Stage construction works are complete.
Complete

Statement of Compliance

Council and Relevant Authorities complete audit and inspections. Roads and services are approved. Council provides Statement of Compliance confirming works are complete per the approved plans and to the satisfaction of all Relevant Authorities.
Complete

Titles and Settlement

Registration of Titles for each lot by Land Titles Victoria as per the plan of subdivision and the surveyor's report. With the legal transfer of the lot to the developer to the purchaser on settlement
Stage Titled
Disclaimer: Please note that all timeframes are estimated only, are reviewed constantly and are often subject to third party approvals and works occurring as scheduled, and do not take inclement weather into consideration.

Stage 4

Construction Complete
100%%
Forecast Completion: Complete
* Titles are expected within 6 weeks of construction completion
Construction Phase Completed

Stage Planning and Permits

Council and Relevant Authority acceptance and approval of documentation, including engineering design to allow for Stage work to commence on site.
Complete

Bulk Earthwork

Earthworks for construction of the Stage.
This work includes removing topsoil and the cutting and filling of the land within the Stage to achieve suitable surface levels for roadways and each lot.
Complete

Drainage

The construction and installation of underground drainage services.
These services include the provision of drainage for roads, public areas and a drainage point for each lot within the Stage.
Complete

Sewer

The construction and installation of underground sewer services.
Sewer works include the provision of trunk sewers and the reticulation of sewer pipelines. Sewer connection points are provided to each lot within the Stage.
Complete

Water and Gas Services

The installation of water and gas pipelines. Connection points are provided to each lot within the Stage.
Complete

Road Boxing, Kerb and Channel

Ground preparations. Construction of base and lower layers of roads. Build kerbs to border the roadways and channels for drainage of rainwater.
Complete

Electrical and NBN

The installation of electrical services and NBN (for high-speed internet) with connection points provided for lots within the Stage.
Complete

Footpaths and Asphalt

Preparation of ground surfaces for the installation of footpaths. Install footpaths and topsoil nature strips within the Stage. Construction of middle pavement layers and asphalt road surfaces.
Complete

Testing

Authority testing of essential services
In progress

Practical Completion

Stage construction works are complete.
Complete

Statement of Compliance

Council and Relevant Authorities complete audit and inspections. Roads and services are approved. Council provides Statement of Compliance confirming works are complete per the approved plans and to the satisfaction of all Relevant Authorities.
Complete

Titles and Settlement

Registration of Titles for each lot by Land Titles Victoria as per the plan of subdivision and the surveyor's report. With the legal transfer of the lot to the developer to the purchaser on settlement
Stage Titled
Disclaimer: Please note that all timeframes are estimated only, are reviewed constantly and are often subject to third party approvals and works occurring as scheduled, and do not take inclement weather into consideration.

Stage 5

Construction Complete
100%
Forecast Completion: March 2020
* Titles are expected within 6 weeks of construction completion
Construction Phase Completed

Stage Planning and Permits

Council and Relevant Authority acceptance and approval of documentation, including engineering design to allow for Stage work to commence on site.
Complete

Bulk Earthwork

Earthworks for construction of the Stage.
This work includes removing topsoil and the cutting and filling of the land within the Stage to achieve suitable surface levels for roadways and each lot.
Complete

Drainage

The construction and installation of underground drainage services.
These services include the provision of drainage for roads, public areas and a drainage point for each lot within the Stage.
Complete

Sewer

The construction and installation of underground sewer services.
Sewer works include the provision of trunk sewers and the reticulation of sewer pipelines. Sewer connection points are provided to each lot within the Stage.
Complete

Water and Gas

The installation of water and gas pipelines. Connection points are provided to each lot within the Stage.
Complete

Road Boxing, Kerb and Channel

Ground preparations. Construction of base and lower layers of roads. Build kerbs to border the roadways and channels for drainage of rainwater.
Complete

Electrical and NBN

The installation of electrical services and NBN (for high-speed internet) with connection points provided for lots within the Stage.
Complete

Footpaths and Asphalt

Preparation of ground surfaces for the installation of footpaths. Install footpaths and topsoil nature strips within the Stage. Construction of middle pavement layers and asphalt road surfaces.
Complete

Testing

Authority testing of essential services
Complete

Practical Completion

Stage construction works are complete.
Complete

Statement of Compliance

Council and Relevant Authorities complete audit and inspections. Roads and services are approved. Council provides Statement of Compliance confirming works are complete per the approved plans and to the satisfaction of all Relevant Authorities.
Complete

Titles and Settlement

Registration of Titles for each lot by Land Titles Victoria as per the plan of subdivision and the surveyor's report. With the legal transfer of the lot to the developer to the purchaser on settlement
Stage Titled
Disclaimer: Please note that all timeframes are estimated only, are reviewed constantly and are often subject to third party approvals and works occurring as scheduled, and do not take inclement weather into consideration.